NCB-STG-11: Procurement of Control & R...

Go Back
Procurement Details

Raised Grievances

Every grievance filed against this reference, with the official GRC decision and the time it took to redress.

0 Cases
0 Resolved
0 Rejected
Mr. Muazzam Fazal
Convener

General Manager

Department: Gujranwala Electric Power Company Limited (GEPCO)

Email: gmtechnical123@gmail.com

Mr. Mazhar Naveed
Member

General Manager

Department: Gujranwala Electric Power Company Limited (GEPCO)

Email: naveedmzr@hotmail.com

Mr. Unser Mehmood
Member

Chief

Department: Gujranwala Electric Power Company Limited (GEPCO)

Email: Gepcolegal@gmail.com

No Grievance Raised

No grievances have been raised for this procurement.

Procurement Committee Details
Mr. Mirza Faisal Nafees Yousaf
Convener

Chief Engineer

Department: Gujranwala Electric Power Company Limited (GEPCO)

Email: cedevgepco@gmail.com

Mr. Amir Mehmood
Member

Director

Department: Gujranwala Electric Power Company Limited (GEPCO)

Email: pmugepco.manager@gmail.com

Mr. Tariq Mehmood
Member

Director

Department: Gujranwala Electric Power Company Limited (GEPCO)

Email: tariqamjadadg@gmail.com

Mr. Imran Tufail
Member

Deputy Director

Department: Gujranwala Electric Power Company Limited (GEPCO)

Email: gso.circle2013@gmail.com

Mr. Muhammad Zafar Ullah Khan
Member

Deputy Director

Department: Gujranwala Electric Power Company Limited (GEPCO)

Email: zafarullahwattoo0481@gmail.com

Clarifications

Query
REQUEST FOR CLARIFICATION / REVISION OF QUALIFICATION CRITERIA – NCB-STG-11: PROCUREMENT OF CONTROL & RELAY PANELS UNDER GEPCO’S OWN RESOURCES

Please find the attachment below.

View PDF Submitted on: Aug 28, 2026, 10:09 AM
Clarification
REQUEST FOR CLARIFICATION / REVISION OF QUALIFICATION CRITERIA – NCB-STG-11: PROCUREMENT OF CONTROL & RELAY PANELS UNDER GEPCO’S OWN RESOURCES

The terms and conditions stipulated in the bidding documents have been duly approved by the competent Authority. Accordingly, you are required to submit your bid strictly in accordance with the approved terms and conditions contained therein.

Responded on: Sep 02, 2026, 10:22 AM

Query
REQUEST FOR CLARIFICATION / REVISION OF QUALIFICATION CRITERIA – NCB-STG-11: PROCUREMENT OF CONTROL & RELAY PANELS UNDER GEPCO’S OWN RESOURCES

Please find the attachment below.

View PDF Submitted on: Aug 28, 2026, 10:13 AM
Clarification
Clarification Reply

The terms and conditions stipulated in the bidding documents have been duly approved by the competent Authority. Accordingly, you are required to submit your bid strictly in accordance with the approved terms and conditions contained therein.

Responded on: Sep 02, 2026, 10:21 AM
There are no pending clarifications.
Pre Bid Meeting
No pre-bid meeting has been conducted.
Corrigendum
3
# Corrigendum Number Corrigendum Date Old Document New Document
1 CORR-P98128-003 Wednesday, September 2, 2026 10:23 AM View PDF View PDF
2 CORR-P98128-002 Friday, August 28, 2026 10:37 AM View PDF View PDF
3 CORR-P98128-001 Monday, August 24, 2026 03:21 PM View PDF View PDF

⏳ Time Left for Bid Submission Deadline

00
Days
00
Hours
00
Minutes
00
Seconds