SSGC/LP/EPADS2/PT/2181288 (P.E PIPE 25...

Go Back
Procurement Details

Raised Grievances

Every grievance filed against this reference, with the official GRC decision and the time it took to redress.

0 Cases
0 Resolved
0 Rejected
Mr. Sajid Sharif
Convener

Manager

Department: Sui Southern Gas Company Limited (SSGCL)

Email: sajid.veryamani@ssgc.com.pk

Mr. Naushad Siddiqui
Member

General Manager

Department: Sui Southern Gas Company Limited (SSGCL)

Email: naushad.siddiqui@ssgc.com.pk

Mr. Tanweer Ahmed
Member

Manager

Department: Sui Southern Gas Company Limited (SSGCL)

Email: tanweer.ahmed@ssgc.com.pk

No Grievance Raised

No grievances have been raised for this procurement.

Procurement Committee Details
Mr. Syed Akbar Hussain Rizvi
Convener

Manager

Department: Sui Southern Gas Company Limited (SSGCL)

Email: akber.hussain@ssgc.com.pk

Mr. Syed Waqar ul Hassan
Member

Deputy Manager

Department: Sui Southern Gas Company Limited (SSGCL)

Email: syed.waqar@ssgc.com.pk

Mr. Khushnaveed Ahmed
Member

Manager

Department: Sui Southern Gas Company Limited (SSGCL)

Email: khushnaveed.ahmed@ssgc.com.pk

Clarifications
No clarification requests have been received.

Clarification Request – Lead Time Extension to 06 Weeks for PE Supply – Tender SSGC/LP/EPADS2/PT/2181288

We are submitting this formal clarification request regarding the delivery lead time specified in the above-referenced tender document for the supply of Polyethylene (PE) materials.

We respectfully request SSGC to kindly consider amending the required delivery lead time to a minimum of 06 (six) weeks from the date of issuance of the Purchase Order (PO).

This request is necessitated by the ongoing worldwide supply chain disruptions, delayed voyages, port congestion, and vessel unavailability affecting approved suppliers of PE raw materials. These global constraints are beyond our control and are significantly impacting the timely availability of raw materials, production scheduling, quality testing, and international shipping logistics.

We assure you of our full commitment to quality and timely execution, provided we are granted this reasonable lead time to manage procurement, manufacturing, and logistics effectively. We kindly request SSGC to issue a formal clarification or addendum to the tender so that all bidders may align their offers accordingly.

We look forward to your favorable response.

Submitted on: Sep 07, 2026, 05:48 PM

Clarification Request – Lead Time Extension to 06 Weeks for PE Supply – Tender SSGC/LP/EPADS2/PT/2181290

We are submitting this formal clarification request regarding the delivery lead time specified in the above-referenced tender document for the supply of Polyethylene (PE) materials.

We respectfully request SSGC to kindly consider amending the required delivery lead time to a minimum of 06 (six) weeks from the date of issuance of the Purchase Order (PO).

This request is necessitated by the ongoing worldwide supply chain disruptions, delayed voyages, port congestion, and vessel unavailability affecting approved suppliers of PE raw materials. These global constraints are beyond our control and are significantly impacting the timely availability of raw materials, production scheduling, quality testing, and international shipping logistics.

We assure you of our full commitment to quality and timely execution, provided we are granted this reasonable lead time to manage procurement, manufacturing, and logistics effectively. We kindly request SSGC to issue a formal clarification or addendum to the tender so that all bidders may align their offers accordingly.

We look forward to your favorable response.

Submitted on: Sep 07, 2026, 05:44 PM
Pre Bid Meeting
No pre-bid meeting has been conducted.
Corrigendum
1
# Corrigendum Number Corrigendum Date Old Document New Document
1 CORR-P93799-001 Saturday, September 5, 2026 02:45 PM View PDF View PDF