Every grievance filed against this reference, with the official GRC decision and the time it took to redress.
Director
Department: National Telecom Corporation (NTC)
Email: mushtaq.ahmad@ntc.org.pk
Director Finance
Department: National Telecom Corporation (NTC)
Email: farhan.feroze@ntc.org.pk
Divisional Engineer
Department: National Telecom Corporation (NTC)
Email: sagheer.syed@ntc.org.pk
No grievances have been raised for this procurement.
Director
Department: National Telecom Corporation (NTC)
Email: muhammad.saeed@ntc.org.pk
Divisional Engineer
Department: National Telecom Corporation (NTC)
Email: qaiser.shehzad@ntc.org.pk
Assistant Director
Department: National Telecom Corporation (NTC)
Email: sajid.ch@ntc.org.pk
Assistant Director
Department: National Telecom Corporation (NTC)
Email: ntc.auditdirmultan@ntc.org.pk
Divisional Engineer
Department: National Telecom Corporation (NTC)
Email: abdul.wahid@ntc.org.pk
Dear Sir,
We intend to participate in tender, delivery/completion period mention in tender documents is 30 days wherease we have to quote imported batteries and import takes almost 14 weeks.
Can we quote our own delivery period or strict with the mentioned 30 days period.
Early reply will enable us to submit quotation timely.
Best Regards
Benchmark Technologies
Submitted on: Sep 05, 2026, 04:17 PM
AOA
Dear Benchmark Technologies Team
It is clarified that Completion/Delivery Period will be as per tender clause i.e. 30xDays.
Regards
Assistant Director (Tech) NTC Multan
Responded on: Sep 07, 2026, 10:01 AM