Every grievance filed against this reference, with the official GRC decision and the time it took to redress.
Deputy Director General
Department: Pakistan Airports Authority (PAA)
Email: ddg.paa@paa.gov.pk
Additional Director
Department: Pakistan Airports Authority (PAA)
Email: khizer.malik69@gmail.com
Deputy Director
Department: Pakistan Airports Authority (PAA)
Email: arslanghous@paa.gov.pk
No grievances have been raised for this procurement.
Deputy Director
Department: Pakistan Airports Authority (PAA)
Email: muneer.alam@paa.gov.pk
Senior Joint Director
Department: Pakistan Airports Authority (PAA)
Email: asma.akhlaq@paa.gov.pk
Deputy Director
Department: Pakistan Airports Authority (PAA)
Email: Subhash.Chander@paa.gov.pk
Dear Sir,
Please find attached our letter regarding the Request for Extension in Bid Submission Deadline & Reduction in Bid Security for the tender “Procurement of Cargo Vehicle Scanner for JIAP Karachi” (Tender No. HQPAA/1992/372/XXLN).
We kindly request you to review the attached letter and consider our requests for a four (04) weeks extension in the bid submission deadline and reduction in the Bid Security.
Your kind consideration and support in this matter would be highly appreciated.
View PDF Submitted on: Sep 07, 2026, 02:52 PM
Dear Sir:
Please find attached Clarification letter.
View PDF Submitted on: Sep 04, 2026, 04:07 PM
Dear Sir:
We would like to seek your confirmation regarding the Bid Security.
Please confirm whether the Bid Security amount equivalent to USD in Pakistani Rupees (PKR) is acceptable to you.
We would appreciate your confirmation in this regard.
Submitted on: Sep 04, 2026, 03:57 PM
Dear Sir/Madam,
We are Submitting Queries and Clarifications in attached file against subjected tender.
Many thanks in anticipation.
Regards,
View PDF Submitted on: Aug 17, 2026, 03:19 PM
1. The tender documentation mentions the detection of nuclear/radioactive material, but no detailed specifications or technical requirements for a Radiation Portal -Monitor (RPM) have been provided. Please confirm whether an RPM is required to be supplied as part of the cargo scanner system. If required, please provide the required technical specifications, detection sensitivity, alarm criteria, installation arrangement, and applicable standards.
2. The tender mentions container identification/tracking, but it is unclear whether a Container Code Reader (CCR) is required as part of the proposed system. Please confirm whether a CCR is required. If container tracking is required, please clarify the intended tracking methodology
3. Please confirm where the centralized monitoring/display system is required to be physically installed
4. If integration with existing airport systems is required, please provide the details of the existing systems, communication protocols, APIs, database interfaces, network architecture, and data formats that will be made available to the cargo scanner supplier
Submitted on: Aug 15, 2026, 09:03 PM
1. Exact location where the scanner is supposed to be placed
2. Will the power be supplied by PAA onsite or we would require a generator for power?
3. Will there be any fencing required at the scanning area? If yes, how much area will be allowed for fencing.
4. The scanner have external alarm, please confirm the aound of alarm wont make any unnecessary disturbance in the area
5. Why each tender requires a separate centralized monitoring system for each type of product when a centralized system for all products can be provided collectively?
Submitted on: Aug 15, 2026, 08:57 PM
With reference to the subject tender, we are pleased to submit the attached clarification letter for your kind review, consideration, and further necessary action.
View PDF Submitted on: Aug 12, 2026, 04:46 PM
Dear Sir/Madam,
Please find attached our consolidated technical, commercial and contractual clarifications/amendment requests with reference to the subject procurement and the discussions held during the pre-bid meeting.
You are kindly requested to review the attached points and provide the necessary clarification/amendment through EPADS / corrigendum / addendum, as applicable, so that all prospective bidders may prepare their proposals on a clear and uniform basis.
Your early response will be highly appreciated.
Best regards.
View PDF Submitted on: Aug 12, 2026, 01:01 PM
Dear Sir/Madam,
With reference to the subject tender, we respectfully request your kind consideration for a 50% reduction in the Bid Security requirement. Considering the substantial amount currently prescribed, such a reduction would encourage wider participation from qualified bidders while maintaining a competitive procurement process.
We also request an extension of the bid submission deadline by four (04) weeks from the current closing date. The additional time will enable bidders to complete the necessary coordination with international OEMs, obtain the required technical and commercial documentation, and prepare comprehensive and competitive proposals.
We trust that our request will receive your favorable consideration and look forward to your positive response.
Submitted on: Aug 04, 2026, 04:15 PM
Dear Sir/Madam,
With reference to the subject tender, we kindly request a 50% reduction in the Bid Security amount, as the current requirement appears to be on the higher side.
We also request an extension of the bid submission deadline by one (1) month from the current submission date to allow sufficient time for OEM coordination and completion of the required documentation.
We would appreciate your kind consideration and look forward to your favorable response.
Submitted on: Jul 30, 2026, 01:04 PM⏳ Time Left for Bid Submission Deadline