PMU-01/2026-27 (ICB) 145KV SF-6 Gas Ci...

Go Back
Procurement Details

Raised Grievances

Every grievance filed against this reference, with the official GRC decision and the time it took to redress.

PMU-01/2026-27 (ICB) 145KV SF-6 Gas Circuit Breakers
1 Cases
0 Resolved
0 Rejected
Mr. Syed Jawad Mansoor Ahmad
Convener

Chief

Department: Multan Electric Power Company (MEPCO)

Email: syedjmahmad@yahoo.com

Login ID: F00376-33-00007

Phone: +92-310-711-4444

Mr. Mian Ansar Mahmood
Member

Chief

Department: Multan Electric Power Company (MEPCO)

Email: fd@mepco.com.pk

Login ID: F00376-33-00008

Phone: +92-311-307-4444

Mr. Shoukat Hussain
Member

Director

Department: Multan Electric Power Company (MEPCO)

Email: engr.shoukathussain@gmail.com

Login ID: F00376-33-00006

Phone: +92-311-405-4444

In_progress

PRE-BID COMPLAINT UNDER RULE 48 OF THE PUBLIC PROCUREMENT RULES, 2004 READ WITH THE REDRESSAL OF GRIEVANCES REGULATIONS, 2021, AGAINST RESTRICTIVE, AMBIGUOUS AND INTERNALLY CONTRADICTORY CLAUSES OF THE BIDDING DOCUMENTS OF TENDER NO. PMU-01/2026-27 (ICB)

GR0-P55310-001 Submitted on Friday, July 17, 2026 06:34 PM Mutahir Metal Works (Pvt.) Limited

A. FACTS
1. That we M/s Mutahir Metal Works (Pvt) Ltd Lahore is a firm engaged in the supply of high voltage electrical equipment, including grid station items to Distribution Companies and other public sector utilities, and is a prospective bidder in the subject procurement, having downloaded the bidding documents from EPADS v2.0.
2. That MEPCO (Procuring Agency) issued a request for Bids for Tender No. PMU-01/2026-27 (ICB) 145KV SF-6 Gas Circuit Breakers, Reference No. P55310, published on EPADS v2.0 on 11.07.2026, for the procurement of 48 sets of 145KV SF-6 Gas Circuit Breakers on Single Stage Two Envelope basis under the Least Cost Based Selection (LCBS) technique, with a bid security of PKR 10,080,000, a bid submission deadline of 11.08.2026 at 10:00 AM, and bid opening on the same day at 10:30 AM.

GRC_Complaint_Mutahir_Metal_CB_MEPCO_PMU-01-2026-27.pdf
Uploaded Friday, July 17, 2026 06:34 PM
Grievance Document
Grievance Redressal Committee
Vendor Relations & Compliance
Response issued on Monday, July 20, 2026 04:39 PM

Pre bid meeting may be arranged with complainant firm and the issues raised through complaint may be resolved as per PPRA Rule.

# Name User ID Designation Department Email Phone Role
1 Mr. Farhan Shabbir Malik F00376-33-00027 Chief Multan Electric Power Company (MEPCO) chiefts@mepco.com.pk +92-310-737-4444 Convener
2 Mr. Muhammad Siddique F00376-31-00015 Manager Multan Electric Power Company (MEPCO) erppmu.proc@mepco.com.pk +92-310-377-4444 Member
3 Mr. Muhammad Rafiq Kanwal F00376-33-00029 Additional Chief Engineer Multan Electric Power Company (MEPCO) managerte@mepco.com.pk +92-310-315-4444 Member
4 Mr. Najib Afzal F00376-33-00030 Manager Multan Electric Power Company (MEPCO) afzalnajib@gmail.com +92-333-610-2767 Member
5 Mr. Yasir Farooq F00376-33-00046 Deputy Director Multan Electric Power Company (MEPCO) tecpmumepco@gmail.com +92-319-976-5972 Member
6 Mr. SHAMS.UL.HAQUE SHAIKH F00376-33-00048 Deputy Director Multan Electric Power Company (MEPCO) engrshamsulhaqueshaikh@gmail.com +92-300-873-1044 Member
7 Mr. Imran Majeed F00376-33-00045 Manager Multan Electric Power Company (MEPCO) managerpssq@mepco.com.pk +92-311-221-4444 Member